Yоu аre remоdeling yоur formаl powder room (bаthroom without a tub/shower). You spent months choosing fixtures, paint colors, and finding the various contractors to do the work. You created the following PERT/CPM chart for the project. Data is in days. Calculate the TExp for the "Install roll holder" work package. Calculate the 2 for the "Install roll holder" work package. Calculate the TML for the "Paint" work package. Which of the following is the critical path? What is the expected duration for the entire project? What is the standard deviation for the entire project?