Tо increаse cаpаcity, a prоject team must decide between twо weaving looms. Both looms have comparable capacity and quality levels, but different costs. The team must evaluate the costs over a five-year study period, with an MARR (an interest rate) of 8% per year. Loom 2: The Jurgens Loom will cost $9,500 now, have operating costs of $1,000 per year, and have a salvage value of $2,500 after 5 years. What is the net present worth of the cash flows for Loom 2? [loom2] The net present worth of the cash flows for Loom 1 is −$12,470. Which loom should the team select? [select]