Belоw is а GANTT chаrt imаge: Hоw lоng is the duration of the project? (2 pts) Can the whole project be done in a shorter duration? (1 pt) Can activity F be done before activity E? (2 pts) Can activity E be done before G is over? (2 pts) How long is the total duration of activities H, I and J? (2 pts) Can activity E start before activity D is over? (2 pts) What is one of the prerequisites of activity J? (2 pts) Is activity C a prerequisite of activity D? (2 pts) Any use of AI will result in a grade of zero on the WHOLE assignment.